VGT1 6.5m Mirror Casting Web Index

Approximate schedule of glass melting:
Thursday, April 25, 2019
  15:00 MST  Furnace starts turning  (750 C)
  17:00 MST  Furnace rotating at 7.3 RPM (762 C)
  19:00 MST  Noticeable glass softening (810 C)
  21:30 MST  Glass blocks slumping (850 C)
  23:50 MST  Glass melting        (900 C)
Friday, April 26, 2019
  04:40 MST  Smoothing of glass surface (980 C)
  09:40 MST  Glass clear          (1070 C)
  13:40 MST  Maximum Temeperature (1165 C)
  17:00 MST  Start cooling        (1165 C)