Large Binocular Telescope Project

Attachment A to the RFP for the

ENCLOSURE CRANES

STATEMENT OF WORK

July 8, 1997

TABLE OF CONTENTS

1. Description of Tasks

2. Procedures

3. Documents

================================================

1. Description of Tasks

1.1 Supply Description

1.1.1 Enclosure Cranes

This Statement of Work covers the design and manufacture of two (2) double girder EOT Maintenance Crane Systems for the Large Binocular Telescope enclosure. Each will be designed for identical lifting capacity, with double trolleys and an independent auxiliary hoist. However, both the bridge span and the hook lift height are different for the two cranes. The lifting capacity is to be 55 metric tons for each bridge, 32 metric tons for each individual trolley and 5 metric tons for the auxiliary hoists. The supply will include the all the supporting hardware items such as the flexible festoon feeding lines and junction boxes, interface compatibility for the portable radio command capability, an emergency control push button station/hand paddle with a 12 m cable. The electro­mechanical components will be standardized for all four trolleys, between the control junction boxes, and between the flexible feed junction boxes. Spare parts will be required as part of the supply.

1.1.2 Technical Specifications

The hardware will be manufactured in accordance with the Large Binocular Telescope Project's Technical Specification "401a014", entitled "Maintenance Cranes for Enclosure and Annex Buildings", revision "e", dated 21 June 1997; and in accordance with the applicable drawings listed below.

1.1.3 Delivery Date

The preferred delivery date for the Enclosure Cranes is 15 July 1998.

The proposal should include a timeline of the Supply activities including shipping to Arizona.

1.1.4 Shipping

Packing for shipment and transportation of the components to Safford, Arizona is included in this Statement of Work.

Please list the shipping costs as a separate item from the price of the main supply.

1.1.5 Technical Assistance during Erection

Technical assistance during final installation in the LBT enclosure on Mt. Graham is included in this Statement of Work.

Please list the cost of the installation assistance as a separate item from the price of the main supply.

1.2 Deliverable Hardware

Listed in the table below are all the hardware components to be delivered as part of this Statement of Work.

Line
Item
Quantity
for Delivery
Drawing
CAN #
Description of Hardware Item
1 1 N/A Crane Assembly for Rotating Building
bridge, two trolley assemblies, auxiliary hoist
2 1 N/A Festoons and Cabling for Rotating Crane
3 1 N/A Control Box for Rotating Crane
4 1 N/A Crane Assembly for Annex Building
bridge, two trolley assemblies, auxiliary hoist
5 1 N/A Festoons and Cabling for Annex Crane
6 1 N/A Control Box for Annex Crane
7 2 N/A Hand Paddles w/ 12 meter cable
8 2 N/A Junction Boxes w/ emergency stop button
9 2 N/A Complete sets of mechanical and electrical "wear parts"

1.3 Deliverable Documents

Described in this section are all the manuals, plans, drawings and documentation that must be supplied as part of this Statement of Work. All documents shall be supplied in four (4) hard copies and one (1) digital copy.

Documentation packages, shall be supplied in support of the following functional activities:

1.3.1 Operations Manual

Prepare and deliver an Operations Manual that shall describe in detail the procedures needed to operate correctly and safely. It shall at least:

1.3.2 Maintenance Manual

The maintenance manual shall contain detailed maintenance procedures with drawings. It shall contain the maintenance requirements and scheduling for all the items included in the supplies of this Statement of Work. Besides the description of the maintenance actions, it shall provide a maintenance checklist with information about:

1.3.3 Acceptance Plan

Prepare and submit for approval an Acceptance Plan describing test procedures and inspections that shall be performed prior to acceptance. The Acceptance Plan must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approved.

The test and inspections shall include:

1.3.3.1 Test Procedures

The Test Procedures shall describe in detail all the necessary operations to perform verification through a test. A Test Procedure shall be produced for every verification test required and shall contain the following information:

The Test Procedure shall be submitted for review prior to performing the test and shall also be incorporated in the specific Test Report.

1.3.3.2 Test Reports

The Test Reports shall summarize the findings of the tests. The Test Report shall be submitted to the LBTC not later than 30 days after the test. A Test Report shall contain the following information:

1.3.4 Spare Parts List

The Spare Part List shall contain all the relevant information concerning the required spare parts recommended for initial operations and for ten years of operation such as:

1.3.5 Drawings

All drawings shall be prepared with AUTOCAD 12 or 13 or compatible format. Where practical all the AUTOCAD drawings produced should comply with the LBT Drawing Standards "001s006". All the workshop assembly and sub-assembly drawings as well as the "as-built" drawings shall include the following information:

1.3.5.1 Design Review

A Design Review package including dimensional drawings and design specifications must be submitted to the Technical Representative for approval before starting the preparation of detailed Workshop Drawings. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.

1.3.5.2 Workshop Drawings

All the workshop drawings must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.

1.3.5.3 As-Built Drawings

The LBTPO shall receive copies of the updated "as-built" drawings and documentation not later than 30 days after the completion of the acceptance tests.

1.3.6 Storage and Shipping Plan

Prepare a storage/shipping plan and submit it to the Technical Representative(s) for approval. The plan should provide detailed instructions regarding unpacking and handling

All steel structures shall be packed in such a way as to guarantee:

1.3.7 Progress Reports to the LBTC

Reports on the status of the work covered by this contract should be sent to the LBTPO every three months. The Progress Report shall include an update of the initially proposed schedule (section 3.6.1 of the Proposal format).

2. Procedures

2.1 Acceptance

The Work shall be conditionally accepted by LBTC upon delivery and completion of the Work in a manner at that time satisfactory to LBTC. Final acceptance will be made subsequent to the installation into the Large Binocular Telescope enclosure or after a time not to exceed 120 days.

2.2 Technical Liaison

The Supplier shall provide access to all phases of the Work to the following LBTC Technical Representative(s):
   Walter Gallieni
   ADS Italia Srl
   Corso Promessi Sposi 23/D
   22053 Lecco
   ITALY

   telephone: 39-341-259-231
   telefax:   39-341-250-560
   email:     ads.gallieni@enet.it
   URL:       http://www.enet.it/ads

The Supplier shall maintain informal technical liaison with the LBT Project Technical Representative(s). These representative(s) shall be provided the following:

All workshop drawings regarding fabrication and construction must be submitted to the LBTC Technical Representative for approval before purchasing any materials and/or beginning any construction.

LBTC approval will cover only the functional and conceptual aspects of the design and will not cover the correctness of the dimensions and practicality of the machining. Approval of the drawings shall not indicate acceptance of the Work.

2.3 Technical Changes

All ECRs, NCRs, and Requests for Waivers or Deviations will be presented to the Technical Representative(s) for further evaluation, formulation of responses, and recommendations to the LBT Director.

2.3.1 Engineering Change Request

In the event that the Supplier deems it necessary to deviate from any specification or term of the Technical Specifications or the Proposal, the Supplier shall deliver to the Technical Representative(s) an Engineering Change Request (ECR) setting forth:

2.3.2 Non-Conformance Report (NCR)

The Supplier shall report all non-conformities from the Technical Specifications which occur during the manufacture, assembly, or testing at all levels of the Work. Each Non-Conformance-Report shall set forth the following:

2.3.3 Request for Waiver/Deviation

A Request for Waiver may be issued during the manufacturing, test or integration of a deliverable item to:

A granted waiver does not lead to changes of any approved and released documents. The Request for Waiver shall include:

It shall be accompanied by all documentation required by the LBT Corporation to judge the acceptability of the waiver. If any change in the schedule or performance are expected, these points shall be clearly addressed.

2.4 Point of Delivery

All documents shipped as a result of this Statement of Work shall be sent to the LBT Project Office:
   LBT Project Office/USA
   The University of Arizona
   Steward Observatory
   Tucson, AZ  85721-0065
   USA

All hardware shipped as a result of this Statement of Work shall be sent to the LBT Staging Area at the Base Camp of the Mount Graham International Observatory:

   Large Binocular Telescope Corporation
   MGIO Base Camp
   1480 W. Swift Trail
   Safford, AZ  85546-8053
   USA

3. Documents

3.1 Applicable Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Technical Specification 401a014e.doc
401a014e.htm
21 Jun 1997 Maintenance Cranes for Enclosure and Annex Buildings

3.2 Reference Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Autocad Drawing 320a003c.dwg 08 Feb 1997 Rotating Building 60t (35t + 35t) Crane,
Parking Position Obscuration
Autocad Drawing 250a006b.dwg 05 Mar 1997 General Assembly,
Crane Obstruction
Autocad Drawing 213m003a.dwg 20 Mar 1997 Third Level Plan
Autocad Drawing 213m010a.dwg 20 Mar 1997 Tenth Level Plan
Autocad Drawing b210m016.dwg 21 Oct 1996 Building Section C-C
Autocad Drawing b210m020.dwg 21 Oct 1996 Wall Section Details
Reference 001s006c.htm 02 Jun 1997 LBT Drawing Standards


Previous Page