Large Binocular Telescope Project

Attachment A to the RFP for the

Telescope Driving Systems

STATEMENT OF WORK

January 7, 1999

TABLE OF CONTENTS

1. Description of Tasks

2. Procedures

3. Documents

================================================

1. Description of Tasks

1.1 Supply Description

1.1.1 Telescope Driving Systems

The supply includes: the construction and assembly of nine driving units (motors), four for each axis plus a spare, and the delivery of one test bench for two units to be used to verify the electromechanical performance of the units. In detail the supply includes:

1.1.2 Technical Specifications

The hardware will be manufactured in accordance with the Large Binocular Telescope Project's Technical Specification "401a002", entitled "Driving Systems", revision "h", dated December 23, 1998; and in accordance with the applicable drawings listed below.

1.1.3 Delivery Date

The preferred delivery date for the Drive Systems is June 30, 1999.

The proposal should include a timeline of the Supply activities including shipping to Milan, Italy where the Factory Pre-Erection of the Telescope Structure will occur.

The Inland frameless motors are due to be shipped from the Kollmorgen plant in Radford, Virginia at the end of January 1999. They should be in the Supplier's factory soon after the contract is awarded.

1.1.4 Shipping

The Supply includes shipping the test bench and the nine assembled drive units to Ansaldo Energia in Milan, Italy.

The items will reside in Milan for approximately one year, and then will be shipped along with the telescope structure to the final erection location on Mt. Graham in Arizona. The Supply does not include shipping the test bench and drive units to Arizona.

Please list the shipping and insurance costs to Milan as separate items from the price of the main supply.

1.1.5 Technical Assistance during Erection

The Pre-Erection of all major telescope components will be required in Milan, Italy before erection of the telescope on Mt. Graham in Arizona. This method has been selected to ensure proper form, fit and functional operation of each and every component of the telescope, before crating and shipment to Arizona. The Pre-Erection activities have been described in general form in the Technical Specification "401e028" , entitled "Telescope Pre-Erection". Technical assistance during pre-erection of the telescope in the factory in Milan for the installation of the Driving Systems is not included in this Supply. The LBTC reserves the right to negotiate for such services at a later time.

1.2 Deliverable Hardware

1.2.1 Hardware to be manufactured or supplied

Listed in the table below are all the hardware components to be delivered as part of this Supply.

Line
Item
Quantity for
Delivery
Drawing CAN # Description of Hardware Item
1 9 520a015
520a016
520a013
460a010
Drive System Housing/Assembly
2 9 N/A Pneumatic Brakes, MWM AFR0200
3 9 N/A Pinion Gears
4 4 520a013 Elevation Support Plates
5 1 520a018 Drive Unit Test Bench
6 48 N/A Alignment Blocks
7 TBD N/A Bolts and Fasteners
8 TBD N/A Pipes and Connectors

Fasteners should be delivered with an excess over the required number. The excess should be 2% of the required number with a minimum of four fasteners for each size and length.

1.2.2 Hardware to be provided by LBTPO

Listed below are the hardware components to be provided by the LBT Corporation for integration with the Telescope Driving System.

Line
Item
Quantity for
Delivery
Drawing CAN # Description of Hardware Item
1 9 460x100 Inland Frameless Motor QT 13704
2 9 TBD Heidenhain RON 806 Encoders or
Inland Tachometer TG--5723A

While the drawings show a Heidenhain RON 806 encoder on each motor, our present plan is to replace these with Kollmorgen/Inland tachometers.

1.3 Deliverable Documents

Described in this section are all the manuals, plans, drawings and documentation that must be supplied as part of this Statement of Work. All documents shall be supplied in four (4) hard copies and one (1) digital copy.

Documentation packages, shall be supplied in support of the following functional activities:

1.3.1 Operations Manual

Prepare and deliver an Operations Manual that shall describe in detail the procedures needed to operate correctly and safely. It shall at least:

1.3.2 Maintenance Manual

The maintenance manual shall contain detailed maintenance procedures with drawings. It shall contain the maintenance requirements and scheduling for all the items included in the supplies of this Statement of Work. Besides the description of the maintenance actions, it shall provide a maintenance checklist with information about:

1.3.3 Acceptance Plan

Prepare and submit for approval an Acceptance Plan describing test procedures and inspections that shall be performed prior to acceptance. The Acceptance Plan must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approved.

The test and inspections shall include:

1.3.3.1 Test Procedures

The Test Procedures shall describe in detail all the necessary operations to perform verification through a test. A Test Procedure shall be produced for every verification test required and shall contain the following information:

The Test Procedure shall be submitted for review prior to performing the test and shall also be incorporated in the specific Test Report.

1.3.3.2 Test Reports

The Test Reports shall summarize the findings of the tests. The Test Report shall be submitted to the LBTC not later than 30 days after the test. A Test Report shall contain the following information:

1.3.4 Spare Parts List

The Spare Part List shall contain all the relevant information concerning the required spare parts recommended for initial operations and for ten years of operation such as:

1.3.5 Drawings

All drawings shall be prepared with AUTOCAD 12 or 13 or 14 or compatible format. Where practical all the AUTOCAD drawings produced should comply with the LBT Drawing Standards "001s006". All the workshop assembly and sub-assembly drawings as well as the "as-built" drawings shall include the following information:

1.3.5.1 Design Review

A Design Review package including dimensional drawings and design specifications must be submitted to the Technical Representative for approval before starting the preparation of detailed Workshop Drawings. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.

1.3.5.2 Workshop Drawings

All the workshop drawings must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.

1.3.5.3 As-Built Drawings

The LBTPO shall receive copies of the updated "as-built" drawings and documentation not later than 30 days after the completion of the acceptance tests.

1.3.6 Storage and Shipping Plan

Prepare a storage/shipping plan and submit it to the Technical Representative(s) for approval. The plan should provide detailed instructions regarding unpacking and handling

All steel structures shall be packed in such a way as to guarantee:

1.3.7 Progress Reports to the LBTC

Reports on the status of the work covered by this contract should be sent to the LBTPO every two months. The Progress Report shall include an update of the initially proposed schedule (section 3.6.1 of the Proposal format).

2. Procedures

2.1 Acceptance

The Work shall be conditionally accepted by LBTC upon delivery and completion of the Work in a manner at that time satisfactory to LBTC. Final acceptance will be made subsequent to the installation into the Large Binocular Telescope or after a time not to exceed 90 days.

2.2 Technical Liaison

The Supplier shall provide access to all phases of the Work to the following LBTC Technical Representative(s):
   Daniele Gallieni
   ADS Italia Srl
   Corso Promessi Sposi 23/D
   22053 Lecco
   ITALY

   telephone: 39-0341-259-231
   telefax:   39-0341-259-235
   email:     ads.dgallieni@enet.it
   URL:       http://www.enet.it/ads

The Supplier shall maintain informal technical liaison with the LBT Project Technical Representative(s). These representative(s) shall be provided the following:

All workshop drawings regarding fabrication and construction must be submitted to the LBTC Technical Representative for approval before purchasing any materials and/or beginning any construction.

LBTC approval will cover only the functional and conceptual aspects of the design and will not cover the correctness of the dimensions and practicality of the machining. Approval of the drawings shall not indicate acceptance of the Work.

2.3 Technical Changes

All ECRs, NCRs, and Requests for Waivers or Deviations will be presented to the Technical Representative(s) for further evaluation, formulation of responses, and recommendations to the LBT Director.

2.3.1 Engineering Change Request

In the event that the Supplier deems it necessary to deviate from any specification or term of the Technical Specifications or the Proposal, the Supplier shall deliver to the Technical Representative(s) an Engineering Change Request (ECR) setting forth:

2.3.2 Non-Conformance Report (NCR)

The Supplier shall report all non-conformities from the Technical Specifications which occur during the manufacture, assembly, or testing at all levels of the Work. Each Non-Conformance-Report shall set forth the following:

2.3.3 Request for Waiver/Deviation

A Request for Waiver may be issued during the manufacturing, test or integration of a deliverable item to:

A granted waiver does not lead to changes of any approved and released documents. The Request for Waiver shall include:

It shall be accompanied by all documentation required by the LBT Corporation to judge the acceptability of the waiver. If any change in the schedule or performance are expected, these points shall be clearly addressed.

2.4 Point of Delivery

All documents shipped as a result of this Statement of Work shall be sent to the LBT Project Office:

   LBT Project Office/USA
   The University of Arizona
   Steward Observatory
   Tucson, AZ  85721-0065
   USA

All hardware shipped as a result of this Statement of Work shall be sent to :


   Large Binocular Telescope Corporation
   c/o Ansaldo Energia S.p.A.
   Viale Sarca, 336
   20126 Milano
   Italia

3. Documents

3.1 Applicable Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Technical Specification 401a002h.doc
401a002h.htm
23 Dec 1998 Driving Systems
Autocad Drawing460a010f.dwg 03 Dec 1998Azimuth Drive Mechanical
Azimuth Drive System
Mounting Geometry
Autocad Drawing460x100a.dwg 16 Dec 1998Azimuth Drive Mechanical
Inland Frameless Motor QT 13704
Outline and Assembly for EL and AZ
Autocad Drawing520a012b.dwg 14 Mar 1997Elevation Drive Mechanical
Elevation Drive Application
C Ring Section
Autocad Drawing520a013f.dwg 03 Dec 1998Elevation Drive Mechanical
Elevation Drive System
Mounting Geometry
Autocad Drawing520a015b.dwg 30 Nov 1998Elevation Drive Mechanical
Drive Unit Housing
Autocad Drawing520a016d.dwg 03 Dec 1998Elevation Drive Mechanical
Drive System
Drive System Mounting
Autocad Drawing520a017b.dwg 22 Jul 1998Elevation Drive Mechanical
Drive System
Pneumatic Plant
Autocad Drawing520a018c.dwg 03 Dec 1998Elevation Drive Mechanical
Drive System
Drive Unit Test Bench

3.2 Reference Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Autocad Drawing407e001c.dwg 15 Jul 1997Telescope Special Utilities
Access to the Telescope
General Layout; 3D View
Autocad Drawing430a010c.dwg 23 Dec 1998Telescope Azimuth Platform
General Assembly
Plant View
Autocad Drawing440a015b.dwg 04 Mar 1997Hydrostatic Supports
General Drawings
Elevation Support View
Autocad Drawing460x004b.dwg 11 Sep 1998General Assembly
Azimuth Rim Gear
Rim Gear Assembly
Autocad Drawing462a010b.dwg 03 Mar 1997Runway Protection Cover
Azimuth Drive Application
Track Section
Autocad Drawing500a010b.dwg 04 Mar 1997General Elevation Assembly
Elevation General Assembly
Zenith Position
Autocad Drawing500a011b.dwg 04 Mar 1997General Elevation Assembly
Elevation General Assembly
Horizon Pointing
Autocad Drawing520x004b.dwg 17 Sep 1998Elevation Drive Mechanical
Elevation Rim Gear
Rim Gear Assembly
Reference 001s006c.htm 02 Jun 1997 LBT Drawing Standards