1. Description of Tasks

1.1 Supply Description

1.1.1 Hydrostatic Bearing System

This Statement of Work includes the manufacture of the Hydrostatic Bearing System for the Large Binocular Telescope. The Supply includes the construction of the Hydrostatic Supports for the azimuth and elevation axes of the Large Binocular Telescope structure together with the design and construction of the related hydraulic equipment and electrical cabinet. The Supply also includes the hydraulic motors and controls of the auxiliary elevation drives of the telescope along with the stow pin mechanisms.

1.1.2 Technical Specifications

The hardware will be designed and manufactured in accordance with the Large Binocular Telescope Project's Technical Specification of Support Systems, "401a003", revision "i", dated July 22, 1997; and in accordance with the applicable drawings listed below.

Additional hardware will be manufactured in accordance with the Large Binocular Telescope Project's Technical Specification of the Measuring Heads, Auxiliary Drives, Stow Pins and Limit Switches "401a006", revision "b", dated July 23, 1997; and in accordance with the applicable drawings listed below.

The Supplier is asked to provide a certain amount of system engineering in the design and manufacture of the hydraulic plant. This will include verification and making the final design of the hydraulic circuits and the hydraulic power plant with the associated electrical and electronic control circuits. The Large Binocular Telescope Project's Technical Report of Supporting Driving and Measuring Systems, "401a001", revision "e", dated March 3, 1997 describes the dimensioning criteria of the supports and the requested performance.

1.1.3 Delivery Date

The preferred delivery date for the Hydrostatic Bearing System is 15 January 1999.

The proposal should include a time line of the Supply activities.

1.1.4 Shipping

Packing for shipment is included in the Supply. Tranportation to the telescope pre-erection site is not included in this Statement of Work.

1.1.5 Technical Assistance during pre-Erection.

The pre-erection of all major telescope components will be required at a "to be determined" location before erection of the telescope on Mt. Graham in Arizona. This method has been selected to ensure proper form, fit and functional operation of each and every component of the telescope, before crating and shipment to Arizona.

Technical assistance during pre-erection of the telescope at the "to be determined" factory location for the installation and start-up of the Hydrostatic Bearing System is included in this Supply.

Technical assistance during final installation on Mt. Graham is not included in this Statement of Work, but the LBTC reserves the right to negotiate for such services at a later time.

1.2 Deliverable Hardware

Listed in the table below are all the hardware components to be delivered as part of this Statement of Work.

Line
Item
Quantity for
Delivery
Drawing CAN # Description of Hardware Item
1 4 440a014 Supports of the Azimuth Axis
2 4 440a012 Vertical Supports of the Elevation Axis
3 4 440a010 Lateral Supports of the Elevation Axis (Floating)
4 4 440a011 Lateral Supports of the Elevation Axis (~Fixed)
5 4 440a017 Hydrostatic Panels
6 1 440a018 Hydraulic Power Plant
7 1 N/A Electrical Cabinet
8 1 N/A Air Compressor Unit
9 2 523a011 Auxiliary Drive Units
10 2 524a010 Stow Pin Units
11 2 470a010
470a011
Azimuth Encoder Mounting Hardware
12 2 530a010
530a011
Elevation Encoder Mounting Hardware

1.3 Deliverable Documents

Described in this section are all the manuals, lists, drawings and general documentation that will be requested to the Supplier as part of this Statement of Work. All documents shall be supplied in four (4) hard copies and one (1) digital copy.

Documentation packages shall be supplied in support of the following functional activities:

1.3.1 Operations Manual

Prepare and deliver an Operations Manual that shall describe in detail the procedures needed to operate correctly and safely. It shall at least:

1.3.2 Maintenance Manual

The maintenance manual shall contain detailed maintenance procedures with drawings. It shall contain the maintenance requirements and scheduling for all the items included in the supplies of this Statement of Work. Besides the description of the maintenance actions, it shall provide a maintenance checklist with information about:

1.3.3 Acceptance Plan

Prepare and submit for approval an Acceptance Plan describing test procedures and inspections that shall be performed prior to acceptance. The Acceptance Plan must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment, the request is to be considered approved.

The test procedures and inspections shall include:

1.3.3.1 Test Procedures

The Test Procedures shall describe in detail all the necessary operations to perform verification through a test. A Test Procedure shall be produced for every verification test required and shall contain the following information:

The Test Procedure shall be submitted for review prior to performing the test and shall also be incorporated in the specific Test Report.

1.3.3.2 Test Reports

The Test Reports shall summarize the findings of the tests. The Test Report shall be submitted to the LBTC not later than 30 days after the test. A Test Report shall contain the following information:

1.3.4 Spare Parts List

The Spare Parts List shall contain all the relevant information concerning the required spare parts recommended for initial operations and for ten years of operation such as:

1.3.5 Drawings

All drawings shall be prepared with AUTOCAD 12 or 13, or compatible format. Where practical, all the AUTOCAD drawings produced should comply with the LBT Drawing Standards "001s006".

All the workshop assembly and sub-assembly drawings as well as the "as-built" drawings shall include the following information:

1.3.5.1 Design Review

A Design Review package including dimensional drawings and design specifications must be submitted to the Technical Representative for approval before starting the preparation of detailed Workshop Drawings. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.

1.3.5.2 Workshop Drawings

All the workshop drawings must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approved.

1.3.5.3 As-Built Drawings

The LBTPO shall receive copies of the updated "as-built" drawings and documentation not later than 30 days after the completion of the acceptance tests.

1.3.6 Progress Reports to the LBTC

Reports on the status of the work covered by this contract should be sent to the LBTPO every three months. The Progress Report shall include an update of the initially proposed schedule (section 3.6.1 of the Proposal format).

2. Procedures

2.1 Acceptance

The Work shall be conditionally accepted by LBTC upon delivery and completion of the Work in a manner at that time satisfactory to LBTC. Final acceptance will be made subsequent to the installation into the Large Binocular Telescope structure or after a time not to exceed 120 days.

2.2 Technical Liaison

The Supplier shall provide access to all phases of the Work to the following LBTC Technical Representative(s):
   Walter Gallieni
   ADS Italia Srl
   Corso Promessi Sposi 23/D
   22053 Lecco
   ITALY

   telephone: 39-341-259-231
   telefax:   39-341-250-560
   email:     ads.gallieni@enet.it
   URL:       http://www.enet.it/ads

The Supplier shall maintain informal technical liaison with the LBT Project Technical Representative(s). These representative(s) shall be provided the following:

All workshop drawings regarding fabrication and construction must be submitted to the LBTC Technical Representative for approval before purchasing any materials and/or beginning any construction.

LBTC approval will cover only the functional and conceptual aspects of the design and will not cover the correctness of the dimensions and practicality of the machining. Approval of the drawings shall not indicate acceptance of the Work.

2.3 Technical Changes

All ECRs, NCRs, and Requests for Waivers or Deviations will be presented to the Technical Representative(s) for further evaluation, formulation of responses, and recommendations to the LBT Director.

2.3.1 Engineering Change Request

In the event that the Supplier deems it necessary to deviate from any specification or term of the Technical Specifications or the Proposal, the Supplier shall deliver to the Technical Representative(s) an Engineering Change Request (ECR) setting forth:

2.3.2 Non-Conformance Report (NCR)

The Supplier shall report all non-conformities from the Technical Specifications which occur during the manufacture, assembly, or testing at all levels of the Work. Each Non-Conformance-Report shall set forth the following:

2.3.3 Request for Waiver/Deviation

A Request for Waiver may be issued during the manufacturing, test or integration of a deliverable item to:

A granted waiver does not lead to changes of any approved and released documents. The Request for Waiver shall include:

It shall be accompanied by all documentation required by the LBT Corporation to judge the acceptability of the waiver. If any change in the schedule or performance are expected, these points shall be clearly addressed.

2.4 Point of Delivery

All documents shipped as a result of this Statement of Work shall be sent to the LBT Project Office:
   LBT Project Office/USA
   The University of Arizona
   Steward Observatory
   Tucson, AZ  85721-0065
   USA

The address for delivery of hardware will be communicated to the Supplier through a letter from the LBTPO.

3. Documents

3.1 Applicable Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Technical Specification 401a003i.doc
401a003i.htm
22 Jul 1997 Support Systems
Technical Specification 401a006b.doc
401a006b.htm
23 Jul 1997 Measuring Heads, Auxiliary Drives, Stow Pins and Limit Switches
Technical Report 401a001e.doc
401a001e.htm
03 Mar 1997 Supporting Driving and Measuring Systems
Autocad Drawing440a010a.dwg 14 Mar 1997Telescope Hydrostatic System
Elevation Lateral Floating Support
Autocad Drawing440a011a.dwg 14 Mar 1997Telescope Hydrostatic System
Elevation Lateral Fix Support
Autocad Drawing440a012a.dwg 14 Mar 1997Telescope Hydrostatic System
Elevation Support
Autocad Drawing440a013c.dwg 03 Mar 1997Telescope Hydrostatic System
Hydrostatic Scheme
Autocad Drawing440a014a.dwg 14 Mar 1997Telescope Hydrostatic System
Azimuth Support
Autocad Drawing440a015b.dwg 04 Mar 1997Telescope Hydrostatic System
Elevation Support View
Autocad Drawing440a017a.dwg 14 Mar 1997Telescope Hydrostatic System
Hydrostatic Panel
Autocad Drawing440a018a.dwg 14 Mar 1997Telescope Hydrostatic System
Oil Control Unit
Autocad Drawing 470a010b.dwg 05 Mar 1997 Azimuth Encoder Mechanical
Azimuth Measuring System, Details
Autocad Drawing 470a011b.dwg 03 Mar 1997 Azimuth Encoder Mechanical
Azimuth Measuring System, General Assembly
Autocad Drawing 500a010b.dwg 04 Mar 1997 Elevation General Assembly
Zenith Position
Autocad Drawing 500a011b.dwg 04 Mar 1997 Elevation General Assembly
Horizon Pointing
Autocad Drawing 523a010b.dwg 21 Jul 1997 Elevation Emergency Drive
Stow Pin and Auxiliary Drive
Autocad Drawing 523a011b.dwg 21 Jul 1997 Elevation Emergency Drive
Auxiliary Drive
Autocad Drawing 524a010b.dwg 21 Jul 1997 Elevation Stow Pin
Stow Pin
Autocad Drawing 530a010b.dwg 05 Mar 1997 Elevation Encoder Mechanical
Elevation Measuring System, Details
Autocad Drawing 530a011b.dwg 04 Mar 1997 Elevation Encoder Mechanical
Elevation Measuring System, General Assembly

3.2 Reference Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Autocad Drawing 430a010b.dwg 03 Mar 1997 Azimuth Platform Structure
General Assembly
Plant View
Autocad Drawing462a010b.dwg 03 Mar 1997Azimuth Drive Application
Track Section
Autocad Drawing520a012b.dwg 14 Mar 1997Elevation Drive Application
C Ring Section
Reference 001s006c.htm 02 Jun 1997 LBT Drawing Standards


Previous Page
Last modified: Tue Jul 29 09:38:57 1997