1. Description of Tasks
2. Procedures
3. Documents
================================================
The supply includes: the construction and assembly of two folding Mirror Covers which protect the two 8.4 meter diameter primary mirrors of the Large Binocular Telescope.
Each Mirror Cover assembly consists of a swing arm with a rotation mechanism to move it “in” and “out” of the M1 mirror axis; and on the swing arm a circular deployable umbrella is supported along with an electromechanical device to "open" and "close" it on the M1 mirror area. The M1 Mirror Cover must be able to be opened and closed in every position, between 0 and 90 degrees, of the elevation structure of the Telescope.
The supply consists of one pair of complete Mirror Covers with a right- and left-handed configuration. Our drawings show the right-hand swing arm.
In detail the supply includes:
The M1 Mirror Cover attaches to the front of the already existing M1 Cell. The M1 Cell structure is not included in this supply.
The hardware will be manufactured in accordance with the Large Binocular Telescope Project's Technical Specification "401a022", entitled "Rotating Supporting Arms with the fabric retractable cover of the Primary Mirrors", revision "d", dated February 26, 2004 and in accordance with the applicable drawings listed below. These drawings represent a quite detailed concept; however we assume that the Supplier will produce their own detailed fabrication drawings which incorporate local best practice and procedure.
The preferred delivery date for the Mirror Covers is November 22, 2004.
The proposal should include a timeline of the Supply of all activities not including packing and shipment.
The Supply does not include packing and shipping of the assembled Mirror Covers. The packing and shipping of the Mirror Covers may be included as an option in the proposal.
Listed in the table below are all the hardware components to be delivered as part of this Supply.
Line |
Quantity for |
Drawing CAN # |
Description of Hardware
Item |
1 |
1 |
727a007 |
Mirror Cover Assembly (Right Location) |
2 |
1 |
similar |
Mirror Cover Assembly (Left Location) |
3 |
TBD |
N/A |
Bolts and Fasteners |
Fasteners should be delivered with an excess over the required number. The excess should be 3% of the required number with a minimum of four fasteners for each size and length.
Described in this section are all the manuals, plans, drawings and documentation that must be supplied as part of this Statement of Work. All documents shall be supplied in two (2) hard copies and one (1) digital copy.
Documentation packages shall be supplied in support of the following functional activities:
Prepare and deliver an Operations Manual that shall describe in detail the procedures needed to operate correctly and safely. It shall at least:
The maintenance manual shall contain detailed maintenance procedures with drawings. It shall contain the maintenance requirements and scheduling for all the items included in the supplies of this Statement of Work. Besides the description of the maintenance actions, it shall provide a maintenance checklist with information about:
Prepare and submit for approval an Acceptance Plan describing test procedures and inspections that shall be performed prior to acceptance. The Acceptance Plan must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approved.
The test and inspections shall include:
1.3.3.1 Test Procedures
The Test Procedures shall describe in detail all the necessary operations to perform verification through a test. A Test Procedure shall be produced for every verification test required and shall contain the following information:
The Test Procedure shall be submitted for review prior to performing the test and shall also be incorporated in the specific Test Report.
1.3.3.2 Test Reports
The Test Reports shall summarize the findings of the tests. The Test Report shall be submitted to the LBTC not later than 30 days after the test. A Test Report shall contain the following information:
The Spare Parts List shall contain all the relevant information concerning the required spare parts recommended for initial operations and for ten years of operation such as:
All drawings shall be prepared with AUTOCAD 2000, MDT6 or compatible format. Where practical all the AUTOCAD drawings produced should comply with the LBT Drawing Standards "001s006". All the workshop assembly and sub-assembly drawings as well as the "as-built" drawings shall include the following information:
1.3.5.1 Design Review
A Design Review package including dimensional drawings and design specifications must be submitted to the Technical Representative for approval before starting the preparation of detailed Workshop Drawings. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.
1.3.5.2 Workshop Drawings
All the workshop drawings must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.
1.3.5.3 As-Built Drawings
The LBTPO shall receive copies of the updated "as-built" drawings and documentation not later than 30 days after the completion of the acceptance tests.
Prepare a storage/shipping plan and submit it to the Technical Representative(s) for approval. The plan should provide detailed instructions regarding unpacking and handling, and should provide the determination of volume and weight in relation to the transportation means.
Reports on the status of the work covered by this contract should be sent to the LBTPO every two months. The Progress Report shall include an update of the initially proposed schedule (section 3.6.1 of the Proposal format).
The Work shall be conditionally accepted by LBTC upon delivery and completion of the Work (including the acceptance tests in the factory) in a manner at that time satisfactory to LBTC. Final acceptance will be made subsequent to the installation into the Large Binocular Telescope or after a time not to exceed 90 days.
The Supplier shall provide access to all phases of the Work to the following LBTC Technical Representative(s):
TECHNICAL REPRESENTATIVE TO BE NAMED AT THE TIME OF CONTRACT AWARD
The Supplier shall maintain informal technical liaison with the LBT Project Technical Representative(s). These representative(s) shall be provided the following:
All workshop drawings regarding fabrication and construction must be submitted to the LBTC Technical Representative for approval before purchasing any materials and/or beginning any construction.
LBTC approval will cover only the functional and conceptual aspects of the design and will not cover the correctness of the dimensions and practicality of the machining. Approval of the drawings shall not indicate acceptance of the Work.
All ECRs, NCRs, and Requests for Waivers or Deviations will be presented to the Technical Representative(s) for further evaluation, formulation of responses, and recommendations to the LBT Director.
2.3.1 Engineering Change Request
In the event that the Supplier deems it necessary to deviate from any specification or term of the Technical Specifications or the Proposal, the Supplier shall deliver to the Technical Representative(s) an Engineering Change Request (ECR) setting forth:
2.3.2 Non-Conformance Report (NCR)
The Supplier shall report all non-conformities from the Technical Specifications which occur during the manufacture, assembly, or testing at all levels of the Work. Each Non-Conformance-Report shall set forth the following:
2.3.3 Request for Waiver/Deviation
A Request for Waiver may be issued during the manufacturing, test or integration of a deliverable item to:
A granted waiver does not lead to changes of any approved and released documents. The Request for Waiver shall include:
It shall be accompanied by all documentation required by the LBT Corporation to judge the acceptability of the waiver. If any change in the schedule or performance are expected, these points shall be clearly addressed.
All documents shipped as a result of this Statement of Work shall be sent to the LBT Project Office:
LBT Project Office/USA The University of Arizona 933 N Cherry Avenue Tucson, AZ 85721-0065 USA
All hardware shipped as a result of this Statement of Work shall be sent to:
Large Binocular Telescope Observatory MGIO Base Camp 1480 W Swift Trail Safford, AZ 85546-8053 USA
The Supplier is not requested for packing and shipment.
Document |
Drawing |
Revision |
Assembly / Part
Name |
Technical Specification |
26 Feb 2004 |
Technical Specification / Rotating Supporting Arms with the fabric retractable cover of the primary mirrors |
|
Autocad Drawing |
23 Jul 2001 |
M1 Mirror Cover |
|
Autocad Drawing |
15 Jul 2001 |
M1 Mirror Cover |
|
Autocad Drawing |
15 Jul 2001 |
M1 Mirror Cover |
|
Autocad Drawing |
23 Jul 2001 |
M1 Mirror Cover |
|
Autocad Drawing |
727a012a.dwg 727a013a.dwg 727a014a.dwg 727a015a.dwg 727a016b.dwg 727a017a.dwg 727a018b.dwg 727a019a.dwg 727a020a.dwg 727a021b.dwg 727a022a.dwg 727a023a.dwg 727a024a.dwg 727a025b.dwg 727a026a.dwg 727a027a.dwg 727a028a.dwg |
|
M1 Mirror Cover |
Autocad Drawing |
727a029a.dwg 727a032a.dwg 727a033a.dwg 727a034a.dwg 727a035a.dwg 727a036a.dwg 727a037a.dwg 727a038a.dwg 727a039a.dwg 727a040a.dwg 727a041a.dwg 727a042a.dwg 727a043a.dwg 727a044a.dwg 727a045a.dwg 727a046a.dwg 727a047a.dwg |
|
M1 Mirror Cover |
Autocad Drawing |
727a048a.dwg 727a049a.dwg 727a050a.dwg 727a051a.dwg 727a052a.dwg 727a053a.dwg 727a054a.dwg 727a055a.dwg 727a056a.dwg 727a057a.dwg 727a058a.dwg 727a059a.dwg 727a060a.dwg 727a061a.dwg 727a062a.dwg 727a063a.dwg 727a064a.dwg 727a065a.dwg 727a066a.dwg 727a067a.dwg 727a068a.dwg 727a069a.dwg 727a070a.dwg 727a071a.dwg 727a072a.dwg 727a073b.dwg |
|
M1 Mirror Cover |
Autocad Drawing | 727a005b.dwg | M1 Mirror Cover M1 Cell Dummy for M1 Mirror Cover |
|
Autocad Drawing | 727a006a.dwg | M1 Mirror Cover Test Bench for Mirror Cover |
Document |
Drawing |
Revision |
Assembly / Part
Name |
Technical Report |
|
13 Jul 2001 |
Technical Report of M1 Covering System |
Autocad Drawing | 721x220c.dwg | 05 Oct 2000 | M1 Cell Construction Drawings M1 Cell "R" -- General Assembly Sheet 1/2 |
Autocad Drawing | 721x221b.dwg | 05 Oct 2000 | M1 Cell Construction Drawings M1 Cell "R" -- General Assembly Sheet 2/2 |
Autocad Drawing | 721x230d.dwg | 05 Oct 2000 | M1 Cell Construction Drawings M1 Cell "R" -- Machining Sheet 1/4 |
Autocad Drawing | 721x231b.dwg | 24 Aug 2000 | M1 Cell Construction Drawings M1 Cell "R" -- Machining Sheet 2/4 |
Autocad Drawing | 721x232d.dwg | 25 Mar 2001 | M1 Cell Construction Drawings M1 Cell "R" -- Machining Sheet 3/4 |
Autocad Drawing | 721x233d.dwg | 05 Oct 2000 | M1 Cell Construction Drawings M1 Cell "R" -- Machining Sheet 4/4 |
Reference | 001s006c.htm | 02 Jun 1997 | LBT Drawing Standards |