Large Binocular Telescope Project

Attachment A to the RFP for the

CENTRAL DEROTATORS' STRUCTURE

STATEMENT OF WORK

January 20, 1998
(Tables 3.1 and 3.2 revised May 04, 1998)

TABLE OF CONTENTS

1. Description of Tasks

2. Procedures

3. Documents

================================================

1. Description of Tasks

1.1 Supply Description

1.1.1 Central Derotators' Structure

This Statement of Work covers the manufacture of the Central Derotators' Structure for the Large Binocular Telescope. These are the sections of the telescope elevation structure which support the central three pairs of focal stations and which support the bearings for the instrument derotators at each of these focal stations. The Supply includes: the preparation of shop drawings, the fabrication, the machining, the pre-assembly and the testing of the steel structure.

1.1.2 Technical Specifications

The hardware will be manufactured in accordance with the Large Binocular Telescope Project's Technical Specification "401e031", entitled "Derotators' Structure Support", revision "b", dated 19 January 1998; and in accordance with the applicable drawings listed below.

1.1.3 Delivery Date

The preferred shipping date for the Central Derotators Structure is 15 June 1999.

The proposal should include a time line of the Supply activities.

1.1.4 Shipping

Packing for shipment is included in the Supply. Tranportation to the Telescope Pre-Erection site is also included in this Supply.

1.1.5 Technical Assistance during Telescope Pre-Erection.

The Pre-Erection of all major telescope components will be required at a "to be determined" location before erection of the telescope on Mt. Graham in Arizona. This method has been selected to ensure proper form, fit and functional operation of each and every component of the telescope, before crating and shipment to Arizona. The Pre-Erection activities have been described in general form in the Technical Specification "401e028" , entitled "Telescope Pre-Erection".

Technical assistance during Pre-Erection of the telescope at the "to be determined" factory location or during final installation on Mt. Graham is not included in this Statement of Work. The LBTC reserves the right to negotiate for such services at a later time.

1.2 Deliverable Hardware

1.2.1 Hardware to be manufactured or supplied

Listed in the table below are all the hardware components to be delivered as part of this Supply.

Line
Item
Quantity for
Delivery
Drawing
CAN #
Description of Hardware Item
1 1+1 513e007 Lower Structure (L&R)
2 1+1 513e008 Upper Structure (L&R)
3 1+1 513e010 Connected Plate for C-Ring (L&R)
4 1+1 513e011 Drag Strut Internal Back (L&R)
5 1+1 513e012 Drag Strut External Back (L&R)
6 2 513e013 Drag Strut Central
7 1 513e015 Connection Strut Frontal
8 1 513e016 Connection Strut Back
9 1+1 513e017 Drag Strut Frontal (L&R)
10 TBD 513e018 Shims (L&R)
11 TBD N/A Bolts and Fasteners

Fasteners should be delivered with an excess over the required number. The excess should be 2% of the required number with a minimum of four fasteners for each size and length.

1.2.2 Hardware to be provided by LBTPO

Listed below are the hardware components to be provided by the LBT Corporation for integration with the Central Derotators' Structure. There are six central focal stations. Four of them have cable wraps while the two in the center have a doubled rotator/derotator bearing. Each of the derotator bearings has a pair of drive motors, while each cable wrap has only a single drive motor.

Line
Item
Quantity for
Delivery
Drawing CAN # Description of Hardware Item
1 16 670a026 Central Rotator Drive Motors
2 16 N/A Rotator Drive Electronics
3 8 670a021 Central Rotator Bearings & Gears
4 4 670a026 Central Cable Chain Drive Motors
5 4 N/A Cable Chain Drive Electronics
6 4 670a023 Central Cable Chain Bearings & Gears

1.3 Deliverable Documents

Described in this section are all the manuals, plans, drawings and documentation that must be supplied as part of this Statement of Work. All documents shall be supplied in four (4) hard copies and one (1) digital copy.

Documentation packages, shall be supplied in support of the following functional activities:

1.3.1 Operations Manual

Prepare and deliver an Operations Manual that shall describe in detail the procedures needed to install correctly and safely. It shall at least:

1.3.2 Acceptance Plan

Prepare and submit for approval an Acceptance Plan describing test procedures and inspections that shall be performed prior to acceptance. The Acceptance Plan must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approved.

The test and inspections shall include:

1.3.2.1 Test Procedures

The Test Procedures shall describe in detail all the necessary operations to perform verification through a test. A Test Procedure shall be produced for every verification test required and shall contain the following information:

The Test Procedure shall be submitted for review prior to performing the test and shall also be incorporated in the specific Test Report.

1.3.2.2 Test Reports

The Test Reports shall summarize the findings of the tests. The Test Report shall be submitted to the LBTC not later than 30 days after the test. A Test Report shall contain the following information:

1.3.3 Drawings

All drawings and relevant parts lists shall be prepared with AUTOCAD 12 or 13 or compatible format. Where practical all the AUTOCAD drawings produced should comply with the LBT Drawing Standards "001s006". All the workshop assembly and sub-assembly drawings as well as the "as-built" drawings shall include the following information:

1.3.3.1 Workshop Drawings

All the workshop drawings must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approval.

1.3.3.2 As-Built Drawings

The LBTPO shall receive copies of the updated "as-built" drawings and documentation not later than 30 days after the completion of the acceptance tests, and at least 15 days prior to acceptance (see below).

1.3.4 Manufacturing Plan

Prepare and submit for approval a Manufacturing Plan that shall list all actions which are planned for manufacture, inspection and testing. The Manufacturing Plan should include a schedule of all activities (e.g. Pert chart) and should reference all relevant documents. Constraints on procurement or deliveries should be identified. The Manufacturing Plan must be submitted to the Technical Representative for approval before starting the construction and materials purchase. The Technical Representative shall comment on the request within 15 days from the receipt, and in the event of no comment the request is to be considered approved.

1.3.5 Progress Reports to the LBTC

Reports on the status of the work covered by this contract should be sent to the LBTPO every three months. The Progress Report shall include an update of the initially proposed schedule (section 3.6.1 of the Proposal format).

2. Procedures

2.1 Acceptance

The Work shall be conditionally accepted by LBTC upon delivery and completion of the Work in a manner at that time satisfactory to LBTC. Final acceptance will be made subsequent to the installation into the Large Binocular Telescope structure during factory Pre-Erection, or after a time not to exceed 120 days from the completion of the Work.

2.2 Technical Liaison

The Supplier shall provide access to all phases of the Work to the following LBTC Technical Representative(s):
   Gianpietro Marchiori
   European Industrial Engineering
   Via Torino #65 D/E
   30170 Mestre (VE)
   ITALY

   telephone: 39-41-531-7906
   telefax:   39-41-531-7757
   email:     eiedir@ve.nettuno.it

The Supplier shall maintain informal technical liaison with the LBT Project Technical Representative(s). These representative(s) shall be provided the following:

All workshop drawings, parts lists and manufacturing plans must be submitted to the LBTC Technical Representative for approval before purchasing any materials and/or beginning any construction.

LBTC approval will cover only the functional and conceptual aspects of the design and will not cover the correctness of the dimensions and practicality of the machining. Approval of the drawings shall not indicate acceptance of the Work.

2.3 Technical Changes

All ECRs, NCRs, and Requests for Waivers or Deviations will be presented to the Technical Representative(s) for further evaluation, formulation of responses, and recommendations to the LBT Director.

2.3.1 Engineering Change Request

In the event that the Supplier deems it necessary to deviate from any specification or term of the Technical Specifications or the Proposal, the Supplier shall deliver to the Technical Representative(s) an Engineering Change Request (ECR) setting forth:

2.3.2 Non-Conformance Report (NCR)

The Supplier shall report all non-conformities from the Technical Specifications which occur during the manufacture, assembly, or testing at all levels of the Work. Each Non-Conformance-Report shall set forth the following:

2.3.3 Request for Waiver/Deviation

A Request for Waiver may be issued during the manufacturing, test or integration of a deliverable item to:

A granted waiver does not lead to changes of any approved and released documents. The Request for Waiver shall include:

It shall be accompanied by all documentation required by the LBT Corporation to judge the acceptability of the waiver. If any change in the schedule or performance are expected, these points shall be clearly addressed.

2.4 Point of Delivery

All documents shipped as a result of this Statement of Work shall be sent to the LBT Project Office:
   LBT Project Office/USA
   The University of Arizona
   Steward Observatory
   Tucson, AZ  85721-0065
   USA

The arrangements for packing and delivery of hardware will be communicated to the Supplier through a letter from the LBTPO.

3. Documents

3.1 Applicable Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Technical Specification 401e031b.doc
401e031b.htm
19 Jan 1998 Central Derotators' Structure
Autocad Drawing513e000a.dwg 30 May 1997Central Structure
Rotator Structure
General View
Autocad Drawing513e002d.dwg 15 Jul 1997Central Structure
Rotator Structure
Orthogonal View
Autocad Drawing513e003d.dwg 15 Jul 1997Central Structure
Rotators Structure
Plan View
Autocad Drawing513e005c.dwg 16 Jun 1997Central Structure
Rotators Structure
Rotator Supp. Lower Back Beam
Autocad Drawing513e006b.dwg 12 Jan 1998Central Structure
Derotators Structure
General Assembly "L"
Autocad Drawing513e007b.dwg 12 Jan 1998Central Structure
Derotators Structure
Lower Structure "L"
Autocad Drawing513e008b.dwg 12 Jan 1998Central Structure
Derotators Structure
Upper Structure "L" Sh.1/3
Autocad Drawing513e009b.dwg 12 Jan 1998Central Structure
Derotators Structure
Upper Structure "L" Sh.2/3
Autocad Drawing513e010b.dwg 12 Jan 1998Central Structure
Derotators Structure
Connected Plate for C-Ring "L"
Autocad Drawing513e011b.dwg 12 Jan 1998Central Structure
Derotators Structure
Drag Strut Internal Back "L"
Autocad Drawing513e012b.dwg 12 Jan 1998Central Structure
Derotators Structure
Drag Strut External Back "L"
Autocad Drawing513e013b.dwg 12 Jan 1998Central Structure
Derotators Structure
Drag Strut Central "L"
Autocad Drawing513e014b.dwg 12 Jan 1998Central Structure
Derotators Structure
Upper Structure "L" Sh. 3/3
Autocad Drawing513e015b.dwg 12 Jan 1998Central Structure
Derotators Structure
Connection Strut Frontal
Autocad Drawing513e016b.dwg 12 Jan 1998Central Structure
Derotators Structure
Connection Strut Back
Autocad Drawing513e017b.dwg 12 Jan 1998Central Structure
Derotators Structure
Drag Strut Frontal "L"
Autocad Drawing513e018b.dwg 12 Jan 1998Central Structure
Derotators Structure
Shims "L"

3.2 Reference Drawings and Documents

Document
Type
Drawing
CAN #
Revision
Date
Assembly / Part Name
Technical Specification 401a010d.doc
401a010d.htm
17 Feb 1997 AZ and Rotators / Instruments Bearings
Autocad Drawing512e005c.dwg 25 Jun 1997Horizontal Bracing
External Nodes
Back Assembly Side "L"
Autocad Drawing512e011c.dwg 16 Jun 1997Elevation Structure
Horizontal Bracing
Lateral Back Beam Side "L"
Autocad Drawing512e039d.dwg 30 Jul 1997Elevation Structure
Horizontal Bracing
Front Beam
Autocad Drawing512e042c.dwg 16 Jun 1997Elevation Structure
Horizontal Bracing
Back Beam
Autocad Drawing512e045c.dwg 16 Jun 1997Elevation Structure
Horizontal Bracing
Rotators Structure
Autocad Drawing514e004d.dwg 30 Jul 97Rolling Sectors
General Assembly Of C-Ring "L"
Autocad Drawing514e006b.dwg 16 May 1997Rolling Sectors
Supporting Arm "L" of Spiders
Autocad Drawing514e023b.dwg 30 Jul 1997Rolling Sectors
General Assembly of C-Ring "R"
Autocad Drawing514e034a.dwg 22 May 1997Rolling Sectors
Supporting Arm "R" of Spiders
Autocad Drawing670a021a.dwg 24 Jan 1997Instrument Rotators
Ball Bearing for Nasmyth and Combined Focus Rotators
Autocad Drawing670a023a.dwg 24 Jan 1997Instrument Rotators
Ball Bearing for Cable Wrap for Nasmyth and Combined Focus Rotators
Autocad Drawing670a025b.dwg 01 Jul 1996Instrument Rotators
Center Area Assembly
Plan View Nasmyth Instruments
Autocad Drawing670a026c.dwg 21 Apr 1997Instrument Rotators
Center Area Assembly
Drive Units Details
Autocad Drawing670a030a.dwg 20 Feb 1997Instrument Rotators
Derotator and Fixed Flange Adaptive Optics Obstruction
Interfaces Details
Autocad Drawing670a031a.dwg 20 Feb 1997Instrument Rotators
Instruments Flange
Interfaces Details
Autocad Drawing670a032a.dwg 20 Feb 1997Instrument Rotators
Fixed Gravity Instrument Interfaces
With Fixation Flange
Autocad Drawing676a001a.dwg 08 Feb 1996Instrument Rotators
Rotator Utilities
Section E-E Detail Cable Wrap
Autocad Drawing407e001c.dwg 15 Jul 1997Telescope Special Utilities
Access to the Telescope
General Layout; 3D View
Technical Specification 401e028e.doc
401e028e.htm
01 Sep 1997 Telescope Pre-Erection
Reference 001s006c.htm 02 Jun 1997 LBT Drawing Standards