Work Packages Released for Bidding | |
Hardpoint Components RFP released on 19 May 2009 Proposals accepted until 08 June 2009
|
|
Mask Manufacturing Unit RFP released on 08 May 2009 Proposals accepted until 15 June 2009
|
|
|
|
Work Packages with Offers Received | |
Dynamic Balancing System Piping Installation RFP released on 21 May 2007 Proposals accepted until 04 June 2007 Revised RFP released on 13 June 2007 Proposals accepted until 29 June 2007
|
|
Mask Manufacturing Unit RFP released on 01 May 2007 Proposals accepted until 01 June 2007
|
|
Tertiary Flat Mirror Polishing RFP released on 09 August 2006. Proposals accepted until 15 September 2006. Proposal deadline has been extended to 29 September 2006. |
|
Thin Secondary Shell RFP released on 28 February, 2006 Proposals accepted until 5 April, 2006 |
|
Telescope Cooling System RFP released on August 26, 2004 Proposals accepted until September 16, 2004 |
|
Telescope M1 Mirror Covers RFP released on April 23, 2004 Proposals accepted until May 27, 2004 The proposal deadline has been extended until June 7, 2004 |
|
Telescope Packing & Transportation RFP released on January 23, 2001 Proposals accepted until February 28, 2001 The proposal deadline has been extended until March 20, 2001 Best and final offers due on May 29, 2001 |
|
Enclosure Cable Chain & Support RFP released on Nov 29, 1999 Proposals accepted until January 12, 2000 The proposal deadline has been extended until January 19, 2000. |
|
Bell Jar Carriage RFP released on September 15, 1999 Proposals accepted until October 14, 1999 |
|
Telescope Swing Arm Spiders RFP released on June 2, 1999; Proposals accepted until July 7, 1999. |
|
Telescope Instrument Rotator Bearings RFP released on March 22, 1999; Proposals accepted until April 21, 1999. The proposal deadline has been extended until April 28, 1999. | |
Telescope Driving Systems RFP released on January 11, 1999; Proposals accepted until February 11, 1999. | |
Telescope Azimuth Radial Bearing RFP released on October 13, 1998; Proposals accepted until November 19, 1998. | |
Pier - Upper Ring Steel Structure RFP released on July 2, 1998; Proposals accepted until August 20, 1998. | |
Central Derotators' Structure RFP was not released for public bid. | |
Rotating Enclosure Gears and Motors Released on November 12, 1997; Proposals accepted until November 25, 1997. The proposal deadline has been extended until December 1, 1997. | |
Elevation Platform and Windbracing RFP released on September 1, 1997; Proposals accepted until October 29, 1997. | |
Azimuth Frame Structure RFP released on September 1, 1997; Proposals accepted until October 29, 1997. | |
Azimuth Ring and C-Ring Structures RFP released on September 1, 1997; Proposals accepted until October 29, 1997. | |
M1 Cells, Bell Jar and Dummy Cell RFP released on September 1, 1997; Proposals accepted until October 29, 1997. | |
Telescope Factory Pre-Erection RFP released on September 1, 1997; Proposals accepted until October 29, 1997. | |
Telescope Pre-Bidding Announcement Distributed on August 8, 1997. See packages below. | |
Hydrostatic Bearing System RFP released on July 30, 1997; Proposals accepted until October 3, 1997.
The proposal deadline has been extended |
|
Enclosure Cranes RFP released on July 9, 1997; Proposals accepted until August 22, 1997.
The proposal deadline has been extended |
|
Enclosure Rotation Bogies and Drives RFP released on June 16, 1997; Proposals accepted until July 23, 1997.
The proposal deadline has been extended |
|
Embedded Beam and Circular Rail RFP released on June 2, 1997; Proposals accepted until July 2, 1997. |
|